Multiple Year Engineering Contract - Plymouth Airport
Plymouth, Massachusetts
Professional Services Provided
- Airport Planning & Engineering
- Transportation & Traffic Engineering
Description of Professional Services
Planning, design and construction services. In addition to work orders listed separately, representative projects over the past ten years include:
Runway 15-33 Reconstruction and Safety Area/Runway Lighting Systems
Design and construction services for 2,500 linear feet of runway reconstruction and widening, installation of taxiway hold signs, construction of two 10,000 square yard safety areas, 1,000 square yard holding apron, and installation of 2,500 linear feet of security fencing.
Designed addition of 200 Medium Intensity Taxiway Lights (MITL's), and 25,000 linear feet of 5Kv Underground Electric Cable, 16,000 linear feet of Bare Copper Counterpoise and Cable Trench. Rewired ten existing Hold Signs and installation of two new Hold Signs, and 380 linear feet of 4-way Underground Electric Duct. To power additional lighting, inadequate 7½Kv regulator was replaced with three 7½Kv and one 15Kv Constant Current Regulators, allowing three levels of intensity controlled manually or by radio transmission. All electrical design was underground and in accordance with FAA standards.
Runway 6-24 Parallel Taxiway Reconstruction
Rehabilitation of Plymouth Airport's 3,500 linear foot, construction of new taxiway on Runway 15-33, installation of taxiway lights along 15-33 parallel taxiway, and construction of security fencing. Responsibilities included collection and evaluation of existing plans, pre-applications, and survey data; preparation of design drawings and specifications and construction cost estimates; and management of bidding and other construction services. During design phase, DuBois & King attended hearings to explain designs and plans to regulatory agencies. Prepared grant applications for submission to FAA and Massachusetts Aeronautics Commission and provided administrative assistance in management of grant monies. Attended preconstruction conference and provided construction management and resident inspection services.
Master Plan Update
Comprehensive Master Plan Update to guide airport development for next 10 to 20 year period. Planning services consisted of intensive review of both ground and air requirements and recommendations for future changes and improvements. Airside elements reviewed included current and future types and levels of airport operations and need for runways, taxiways, holding aprons, and safety areas to support operations.
Groundside elements were reviewed in the context of support for air operation needs. Examined need for new municipal administration building with fixed-base operations center and offices for airport commission, additional corporate and T-hangars, and industrial and commercial development on airport property.
Master planning study included computer-modeled noise level study of both present and projected operations and basic level of environmental impact study for each recommended airside and groundside element.
Throughout planning process, met extensively with Airport Commission and committees of users and citizens. Meetings informed Commission and public of study's progress and obtained information about needs and problems of those who use airport and are affected by its operation.
Fuel Farm Upgrade
Removal of three existing fuel tanks and site monitored for contamination. Installed new 10,000 gallon aboveground Jet A storage tank in steel containment structure. Designed and installed fuel monitoring system for three 12,000 gallon below grade tanks and a 10,000 gallon above grade tank. Designed new fuel dispensing island including kiosks, three dispensing pumps, and new hose reels. Upgraded all piping and installed a cathodic protection system to comply with current environmental and safety codes. Permitting and agency coordination for all construction approvals.
Terminal Area Conceptual Site Plan
Aerial photographic survey and conceptual terminal area layout for airport's proposed T-hangars, corporate hangars, and taxi lanes. Utility planning for water, gas, and sewer to serve all hangars, and site planning (drainage, grading, and utilities) for one T-hangar and two corporate hangars. Assistance and guidance in defining lease lot boundaries for private aviation development.
Apron and Taxiway Evaluation
Pavement evaluation of apron and taxiways to implement an apron crack-sealing and taxiway pavement overlay program with MAC funding assistance.
Wastewater Treatment Facilities Plan
Design phase services and preparation of facilities plan related to needs assessment and evaluation of airport wastewater treatment and disposal alternatives. Developed concept plans to identify future development potential and projected wastewater disposal needs. Available wastewater treatment/disposal alternatives were screened with respect to airport development plan. Construction cost estimates and annual operation and maintenance costs were prepared for each alternative. Coordination with local and state agencies to assess applicability and/or limitations of existing regulations with respect to proposed alternatives. Construction phase services.
Ramp Construction
Designed and assisted in construction of one ramp for 45 aircraft and designed crack sealing on a ramp for over 75 aircraft.
Safety Improvements
Designed 8000 linear feet of perimeter fencing, 16 acres of protection zone clearing, and safety plan. Provided resident inspection and construction administration services for the project.
Fence
8,350-LF, eight-foot-high chain link fence with three 24-foot sliding vehicle gates, four card readers added to existing vehicle gate.
Southwest Terminal Area Planning
Planning, preliminary engineering and permitting for 9,600-LF access road, 1,460 linear feet of taxiway, and a new 210-foot by 300-foot parking apron and up to five new building facilities.
Gate 4 Taxiway
Construction of new 2,000-LF taxiway, including 1,615-LF of six-foot security fence and three vehicle gates.
Terminal Area Service Road
Construction of 9,600-LF new service road.
Instrument Landing System
Feasibility Study
Evaluation of alternative solutions for sewage disposal to replace current subsurface disposal system. Back to Top
|
|