FacebooklinkedininstagramFacebooklinkedininstagram

Washington Electric Co-op Substation Upgrade

 

DuBois & King electrical engineers provided construction administration services, following design services, for the complete rebuild of Washington Electric Co-op’s East Montpelier substation. The project objective was to demolish and replace an existing outdated substation in the same location with a modern, slightly larger, and more efficient facility. The new facility was designed to provide more reliable electric service to approximately 1,640 Washington Electric Co-op members, as well as provide adequate space for future growth.

The project included replacing the existing wooden substation structure and equipment with a galvanized steel structure, three new 1,667 kVA low-loss power transformers, individual circuit regulation, remote monitoring equipment, and solid-state single/three-phase fault protection. The existing overhead distribution feeder exiting the substation was placed underground to the first preexisting distribution pole. The design included oil spill containment in accordance with USDA Rural Utilities Service. In addition to the substation structure, a 12-ft by 8-ft concrete block control building that houses relays and metering equipment was constructed.

D&K engineers worked closely with the Co-op on the development of a construction delivery approach that utilized Co-op labor to complete much of the construction, resulting in considerable cost savings.

Norwich University Electrical Upgrades

 

DuBois & King provided electrical design services for upgrades to the 12.47kV primary service from Northfield Electric to an existing step-down transformer. The project serves the existing Plumley Armory and the Roberts, Webb, and Jackman buildings. The heating plant electrical loop included Doyle and Chaplin Hall, the heating plant, Sabine Field, and the Student Center.

Several alternatives were explored to achieve optimal future expansion, ease of maintenance, and improved aesthetics. Both conventional pad-mounted gear and underground vault mounted equipment options were evaluated and presented in detail. A vault mounted switchgear was selected due to the increased level of safety for operating personnel, improved aesthetics due to below grade installation, and ease of future expansion. The project allowed for removal of overhead distribution lines resulting in aesthetic improvements to the campus. Professional services included:

  • Site analysis of existing service points
    (buildings and overhead tie-in points)
  • Development of electrical technical criteria and design
  • Shop drawing review
  • Bidding assistance
  • Construction phase services

133 State Street Parking Lot and Utilities

 

Montpelier, Vermont, was selected as one of EPA’s “Green Capital” projects from capital cities across the country. The pilot program consisted of retrofitting existing infrastructure with innovative stormwater treatment practices. The concept for this project, developed by others, included renovating an existing parking lot and incorporating stormwater rain gardens.

DuBois & King was retained by the Vermont Department of Buildings and General Services to complete the design, prepare construction documents, and assist in overseeing construction. The project included design for rainwater gardens, parking lot reconstruction, sidewalks, stairways, storm drainage system, sanitary sewer system, and two precast concrete gravity retaining walls to separate the lower parking lot from the upper lot.

Wright’s Covered Bridge

 

Selected by the New Hampshire Division of Historic Resources (NHDHR) to provide consulting services for the historic preservation and rehabilitation of a 124-ft-long, single span truss covered bridge constructed in 1906. The timber trusses (Town Lattice) are augmented with 58-inch-deep, nail-laminated timber arches, which are integral with the chords and web members of the trusses. Project included a Section 106 historical clearance. Design of preservation measures and repairs included:

Installation of a dry sprinkler system
Installation of a linear heat detection system, power, and control
Telemetering of the heat detection system
Application of intumescent paint
Application of fire retardant
Installation of a dry hydrant for a water source
Structural repairs to deteriorated truss members and webs
Repair/replacement of timber bearings, repair of runner planks
Replacement of deteriorated (rotted) siding and timber deck
Application of insecticide at abutments

Principles of the Secretary of the Interior’s Standards for Rehabilitation and the Burlington Charter were applied to all phases of the work.

Woodstock High & Middle School Mechanical/Electrical Upgrades

 

Mechanical, electrical, and structural engineering and construction administration services for upgrades to two facilities totaling 144,000 sf. Assessment of HVAC systems, code compliance, and mechanical design included:

Replacement of noisy air-handling unit
Increased heating capacity for library
New ventilation system for auditorium stage area
Capacity analysis of unit ventilators and hot water heating piping
New make-up air system for kitchen exhaust

Electrical engineering included assessment of existing electrical infrastructure to support new mechanical systems. Provided electrical power floor plans and panel board schedules. Replaced 1957 era panel boards in existing electrical room and six 1957 era disconnects and associated panel boards. Added secondary protection at three 37.5 kVA transformers.

Structural engineering included evaluation of existing system capacity local to new HVAC equipment and design of miscellaneous framing required for support.