Vermont

  • Power Line Tower Assessments 

    The transmission line owner required updated condition information on the foundation and structural support members of 165 high-tension lattice electrical transmission towers. D&K’s structural engineers visited each tower along the entire length of the project, often in remote locations with challenging terrain and access. We used a cloud-based assessment system to allow office personnel to…

  • College St & Marketplace Parking Garages

    Since their construction, Burlington’s largest parking garages had deteriorated, and the city’s operational requirements had evolved. The city also sought to reduce the frequent maintenance activities required to operate the facilities. D&K’s Resident Project Representative provided full-time construction observation and coordination with the city, design engineer, contractors, and subcontractors for improvements to two parking garages:…

  • Randolph Wastewater Treatment Facility

    The 40-year-old wastewater treatment facility, originally designed for a 20-year service life, was past due for a total treatment process change and facility upgrade. The project objectives included: utilize a state-of-the-art treatment process, design capacity for nitrogen removal, consider operational efficiencies and long-term operating costs, address issues with the location in a floodplain, and develop…

  • Statewide Highway Resurfacing

    To efficiently manage the design of highway surfacing and appurtenant systems, the Vermont Agency of Transportation (VTrans) engages consultants to supplement in-house engineering, environmental, and surveying services. Since 1998, D&K has provided design for state and US highways, including interstates, urban Class 1 sections of US or state highways, major and minor arterials, and rural…